Electrical Inspection
Temporary Pole Inspection
Confirm that the disconnect and receptacles are
weatherproof and proper clearance at the point of attachment. In
addition, check conductor capacity, fuses, switches and a check for GFCI for
15 and 20 amp receptacles.
Low Voltage Inspection
Check for integrity, markings on conductors, conductors
are supported properly, conductors are kept 6’ away from attic access and no
more than three (3) outlets per cable.
Rough In Inspection
When wires are run into the building and prior to being
covered by finished walls, ceiling or floors, when the ground wires are made
up to the boxes, the home runs are terminated in the panels, conduit work is
secured (including boxes and nm cable).
Final Inspection
When the job is completed, a final inspection is required.
|